WMD home
regulations
permits
grants/loans
publications
calendar
 
dec home > wmd home > sites home > site pages > gerrish home > february 2003
DEC logo

Contractor Selected for the Corrective Action Plan Implementation at the Gerrish Motors / Woodstock East Site

Community Update #5

Vermont Department of Environmental Conservation

February 2003

Remedial System Operating Successfully  

The Air Sparging/Soil Vapor Extraction (AS/SVE) System at the site has been in operation for approximately five months.  The consultant for the site, ECSMarin of Richmond, Vermont has submitted a report outlining the performance of the remedial system for the first three months of operation.  The ECSMarin report estimates that approximately 310 pounds, or 52 gallons of gasoline have been removed by the AS/SVE system  from the former gaoline underground storage tank area since August.  ECSMarin is currently planning enhancements to the system to increase the recovery rate. 

ECSMarin personnel will be visiting the site regularly to perform maintenance activities and to collect data and samples in Area I that will allow the effectiveness of the AS/SVE system to be evaluated.

 

Excavation Work Completed

ECSMarin also completed excavation of contaminated soils at the site in October.  The final excavation work was the removal of underground pipelines that were connected to the drywell that was discovered in Area 2 earlier this year.  All together, approximately 220 cubic yards of contaminated soils have been removed from Area 2 and disposed of off-site. 

 

The area has been backfilled with clean fill.  At the request of the Gerrish Corporation, the VTDEC is reviewing the corrective action plan (CAP) requirement for interim paving over certain areas of the site.  With the removal of contaminated soil and the placing of clean fill, the risk of exposure to contaminated soils may have been mitigated.  Any proposed changes to the CAP would be announced in a future issue of this newsletter, with an opportunity for the public to comment on the changes.

Water Supply Well Successfully Closed  

The decommissioning of the on-site water was completed on September 12, 2002.  A video survey of this well performed earlier in 2002 revealed that this well was slowly filling itself with native materials.  The well was filled from the bottom to the top with a cement grout.  This will prevent any future use, and also eliminate the chance for contaminants to enter the well from the surface, or to migrate between fractures within the well itself.

 

 

Other Site Issues 

In late December 2002, the parties came to an agreement regarding several of the administrative issues involving this site.  The state agreed to release its lien on the Woodstock East property, granted to it as security as part of the 1999 Settlement agreement.  Release of this lien allowed the Gerrish Corporation to mortgage the property, with the proceeds of the loan paid to the Town of Woodstock to settle the outstanding property tax bill on the property.  The Gerrish Corporation also arranged for purchase of environmental insurance for the site that provides up to $1 million worth of coverage (with a $100,000 deductible) for contamination that might be discovered during the redevelopment of the property.  The term of the policy is 10 years.  Discussions are continuing regarding institutional controls.

 

Questions about the Gerrish Motors / Woodstock East cleanup? Contact the VTDEC Project Manager
Brian Woods
(802) 241-3885
brian.woods@anr.state.vt.us

 



 

VT DEC Waste Mangement Division 103 South Main Street, West Office Building  Waterbury, VT  05671-0404  Tele: 802-241-3888   Fax: 802-241-3296

State of Vermont Agencies & Depts.     Access Government 24/7     About Vermont.Gov     Privacy Policy    Ask a State Librarian a ?

A Vermont Government Website Copyright 2003 State of Vermont - All rights reserved